Know exactly which CDM document is yours to produce.
The OSH (Construction Work) (Design and Management) Regulations 2024 split the paperwork between the client, designers and contractors. Our templates are written for Malaysian projects from the ground up, with every requirement tied to its regulation number.
Who owes what
The main documents under the 2024 Regulations and the duty holder responsible for each.
| Document | Prepared by | Regulation |
|---|---|---|
| Pre-construction information (PCI) | Client, assisted by the PCWD | Reg 5(1) |
| Written appointment of PCWD and PCWC | Client | Reg 7 |
| JKKP 12 notification | Client | Reg 8 |
| Design risk information | Each designer; the PCWD collects it | Regs 11, 12 |
| Construction phase plan (CPP) | PCWC, or the sole contractor | Regs 13, 17 |
| Safety and health file (SHF) | PCWD, where there is more than one contractor | Reg 14 |
| Welfare provision | PCWC, or the sole contractor | Second Schedule |
Where the client is a domestic client, certain client duties pass to the contractor or designer (reg 9). If the client fails to appoint a PCWD or PCWC on a multi-contractor project, the client carries those duties (reg 7(3)).
PCWD: principal construction work designer. PCWC: principal construction work contractor.