Know exactly which CDM document is yours to produce.

The OSH (Construction Work) (Design and Management) Regulations 2024 split the paperwork between the client, designers and contractors. Our templates are written for Malaysian projects from the ground up, with every requirement tied to its regulation number.

Who owes what

The main documents under the 2024 Regulations and the duty holder responsible for each.

DocumentPrepared byRegulation
Pre-construction information (PCI)Client, assisted by the PCWDReg 5(1)
Written appointment of PCWD and PCWCClientReg 7
JKKP 12 notificationClientReg 8
Design risk informationEach designer; the PCWD collects itRegs 11, 12
Construction phase plan (CPP)PCWC, or the sole contractorRegs 13, 17
Safety and health file (SHF)PCWD, where there is more than one contractorReg 14
Welfare provisionPCWC, or the sole contractorSecond Schedule

Where the client is a domestic client, certain client duties pass to the contractor or designer (reg 9). If the client fails to appoint a PCWD or PCWC on a multi-contractor project, the client carries those duties (reg 7(3)).

PCWD: principal construction work designer. PCWC: principal construction work contractor.